In light of the current escalation of hostilities involving Iran and its regional impact, many contracts are facing serious disruptions: sanctions, border or port restrictions, transport‑route closures, and sharply rising logistics or material costs. These developments make it essential for contractual parties to understand what their rights and obligations are under the law and their contract.
Under Saudi law, as well as under model clauses like the ICC Force Majeure and Hardship Clause, parties must distinguish between events that make performance impossible (force majeure) and those that only make it excessively onerous or costly (hardship). In the current environment, decisions taken today—such as whether to issue a force majeure notice, request renegotiation, or continue performance—can determine whether a party preserves its entitlements or risks being treated as in default.
This note explains how Saudi law and the ICC Force Majeure standard clause work together in the current war‑linked situation, and what practical steps each party should consider.
Under the Saudi Civil Transactions Law (CTL), there is no single “force majeure” article, but two key rules define the situation:
Saudi courts treat force majeure as an unforeseeable, beyond the debtor's control event that makes performance impossible, not merely difficult or expensive.
If instead the performance is excessively onerous in such a way that it may cause heavy losses, then the debtor may claim the hardship situation as provided in Article 97 of the CTL which provides that the performance is still possible but excessively onerous.
The ICC Force Majeure and Hardship Clause (2020 / 2023) is a standard model clause that substantially covers extraordinary events beyond a party’s control (such as war, natural disasters, government prohibitions) that prevent performance. Under ICC principle, the consequences are typically suspension of the obligations affected, and, if the event continues for an agreed period, termination of the contract with no liability from the affected party.
The standard clause can be incorporated into contracts by reference. It is widely accepted in international construction and trade and is often used alongside Saudi‑law‑governed contracts.
Under Saudi law, the ICC clause is interpreted:
In practice, Saudi courts and arbitral tribunals will:
Please note that the party invoking successfully the force majeure event is relieved from its duty to perform and from any liability from the time the impediment causes inability to perform, provided that the notice thereof is given without delay. If notice is not given without delay, the relief is effective from the time at which notice thereof reaches the other party
The ICC clause typically defines force majeure by four conditions:
The clause also lists examples such as war, hostilities, acts of terrorism, natural catastrophes, government actions, and similar events. These are presumed force majeure if they genuinely prevent or hinder performance.
In the current context of US/Israel–Iran‑linked tensions, events such as:
may satisfy the ICC‑style force majeure definition if they actually prevent or substantially hinder performance, not just raise costs.
A war or armed conflict can be treated as a force majeure event under the ICC Clause, but only if strict conditions are met:
If the contractor can still perform by using alternative suppliers, routes, or methods (even at higher cost), Saudi‑law‑oriented analysis treats this as hardship (Article 97 CTL), not force majeure.
When an ICC‑style force majeure event is established:
However, the contractor must still:
Saudi‑law‑oriented practitioners emphasise that failure to mitigate or notify may lead the court to deny force majeure protection, even if the event itself qualifies.
The ICC Clause also includes a hardship situation, which instead applies where performance is still technically possible but has become excessively onerous because of an unforeseen event (for example, a major disruption of supply or extreme cost increase). Excessively onerous does not that the performance has become simply more expensive. Under ICC approach, hardship triggers renegotiation; if renegotiation fails, a court or tribunal may adapt or terminate the contract.
Under Saudi Law, Article 97 CTL provides that:
This is very close in spirit to Article 97 CTL, which is mandatory and cannot be waived by contract. Even if the ICC‑style hardship clause is not perfectly aligned with Article 97, Saudi courts will apply the CTL standard as a minimum protection.
In the current war‑related environment:
The party invoking the hardship event is not entitled to suspend the performance just because it sent the request to renegotiate the contract.
If you tell me how your contract refers to the ICC Clause (exact wording) and whether you are the contractor or employer, I can draft a short, ready‑to‑use Model Force Majeure Notice tailored to your project.
[fa icon="phone"] +39 02 0066891
[fa icon="envelope"] manager@bdalaw.it
[fa icon="home"] Via Sant'Orsola 3, Milan Italy